Letter from Coats Rose to Inframark about the Hatch lift station demand (August 7, 2024)

Unofficial searchable copy. For the official record, use the district’s own copy.

Page 1

COATS ROSE
A PROFESSIONAL CORPORATION
BARRY RABON
DIRECTOR
BRABON@COATSROSE.COM
DIRECT: (713) 653-5757
FAX: (713) 890-3947
9 GREENWAY PLAZA, STE 1000, HOUSTON, TEXAS 77046
PHONE: (713) 651-0111 FAX: (713) 651-0220
coatsrose.com
HOUSTON | AUSTIN | DALLAS | CINCINNATI
018330.000008/4869-8083-1957.v1
August 7, 2024
Via E-Mail michael.alpago@inframark.com
and Certified Mail RRR
Inframark, LLC
2002 West Grand Parkway North
Suite 110
Katy, Texas 77449
Attn: Michael Alpago
Re:
Demand for payment, Hatch Lift Station
Dear Mr. Alpago:
In response to your email of July 24, 2024, please see the following:
-
How Inframark allegedly breached its contractual obligations
1. Paragraph 2.6 lists a number of obligations for the Operator. It is reasonable to
expect that any Operator when receiving alarms that the dry well of a lift station
has high water levels would acknowledge the alarms, visit the site, pump down
the water, inspect what caused the water build up, install protective measures to
keep water from building up to damage equipment, and monitor the situation
adequately until resolved.
2. Schedule 1 states that a “Tech” will do “Daily Alarm Checks (Lift Stations)” as
part of their base fee. If daily checks were completed during the window of
being alerted to high water levels and adequate care was implemented at each
visit, then it is reasonable to assume that water would not have built up to a point
of damaging the facility. The virtual log book, physical log book, and work order
history indicate gaps between lift station visits or at minimum gaps between logs
of visiting the site.
3. Schedule 1 states that a “Tech” will “Record and Log Data” as part of their base
fee; daily recordation and logs are not available throughout the window.

Page 2

Michael Alpago
Page 2 of 3
August 7, 2024
-
How Inframark allegedly negligently performed its contractual obligations
1. Based on records provided by Operator,
1. a notification of high-level alarm was received on 2/28/2023 and it was
recorded that the sump pump was not keeping up and one of the pumps was
leaking. The operator logged that they changed the alarm to be email and text
only so it would quit calling but so that they could still keep track;
2. it was logged that they opened the inspection hatch on 3/7/2023 to the dry
well and saw water in the bottom of the dry well. Carlos Perez was called
about the water, and he advised that contractors were working on the problem.
3. it was logged on 3/9/2023 that they were called to the site by customer to
investigate a possible sewer spill. The operator looked around and saw
standing water across the street but notified the customer that the area belongs
to the City of Cedar Park not Inframark. That same day, the Operator was
called to the site for a possible manhole stoppage and found a leak. The
Operator noticed that the wet well and dry well were full and initiated
immediate emergency hauling.
It was negligent to not install a temporary sump pump when it was noticed that the
sump pump was not keeping up and the pumps were leaking; that the alarm method
was modified; that nothing was logged between 2/28 and 3/7; that upon noticing
water in the dry well again on 3/7 again a temporary sump pump was not installed;
that upon being notified of a spill, adequate inspection measures were not conducted
and it took another call to identify the problem.
-
What alleged actions or inactions led to the failure of the Hatch Lift Station
1. modifying the alarm method
2. not adequately addressing alarms, not installing temporary sump pumping, not
repairing pump leak, not setting up for emergency hauling, not checking on
lift station daily per the contract requirements.
-
How Inframark’s alleged actions or inactions led to the failure of the Hatch Lift
Station
1. Because the alarms were modified, the lift station was not checked daily at
minimum per contract, the sump pumps were not assisted with additional
pumping capacity, the pump leak was allowed to continue, the water level
continued to rise over a period of days and submerged the pumps, motors, and

Page 3

Michael Alpago
Page 3 of 3
August 7, 2024
electrical equipment rendering the facility damaged and incapable of normal
operations
-
What damage did the Hatch Lift Station incur and what were the costs for such
damages
1. The pumping & electrical equipment within the dry well required repair and
replacement, the electrical equipment controlling the lift station were rendered
inoperable and required replacement, and the dry well & wet well required
emergency hauling.
-
What engineering and emergency response costs were incurred by WTCMUD1
1. WTCMUD1 paid their previous engineer, Grey Engineering, for their time to
be involved in the emergency situation; paid Inframark for emergency
services; paid sludge hauler for emergency services; paid Alterman for
emergency electrical services; paid Liberty Civil for emergency services.
WTCMUD1 is willing to meet with Inframark prior to mediation. You can coordinate a
meeting with Cole Konopka, Of Counsel with Coats Rose at 713-653-7379 or via email at
ckonopka@coatsrose.com
Thanks, you and please contact me if you need additional information.
Sincerely,
Barry S. Rabon
BSR/mf