Demand letter from Coats Rose to Inframark about the Hatch lift station failure (July 18, 2024)

Unofficial searchable copy. For the official record, use the district’s own copy.

Page 1

COATS ROSE
A PROFESSIONAL CORPORATION
BARRY RABON
DIRECTOR
BRABON@COATSROSE.COM
DIRECT: (713) 653-5757
FAX: (713) 890-3947
9 GREENWAY PLAZA, STE 1000, HOUSTON, TEXAS 77046
PHONE: (713) 651-0111 FAX: (713) 651-0220
coatsrose.com
HOUSTON | AUSTIN | DALLAS | CINCINNATI
018330.000008/4886-9110-0106.v1
July 18, 2024
Via E-Mail makenzi.scales@inframark.com
and Certified Mail RRR
Inframark, LLC
14050 Summit Drive, Suite 103
Austin, Texas 78728
Attn: Makenzi Scales
Re:
Demand for payment, Hatch Lift Station
Dear Ms. Scales:
I represent   (“District”). Inframark,
LLC (“Inframark”), under the Amended and Restated Operation and Maintenance Agreement
(“Agreement”), entered into with the District on March 16, 2022, and acted as Operator for the District’s
water, wastewater, storm water, water quality, part and other governmental facilities providing operations,
maintenance services and accounting services.
The District asserts that Inframark breached the Agreement and/or negligently performed its
services resulting in monetary damages to the District. Specifically, Inframark’s actions and inactions led
to the failure of the Hatch Lift Station and damaged the District by the sum of $551,000.00 (contract with
Liberty Civil). In addition, the District has incurred engineering costs and emergency repairs totaling
$79,092.00 that bring the total cost to $630,092.00. A portion of this has been offset by insurance,
$489,661.10, leaving the District with an out-of-pocket expense of $140,430.90. Demand is made to
Inframark the sum of $140,430.10. If not paid within ten days, the District invokes the mediation
provisions of the agreement to mediate within sixty days. The District reserves its rights to increase these
damages if not resolved with this demand for payment as additional costs for design and operating cost are
under review.
Please let me know how you wish to proceed.
Sincerely,
Barry S. Rabon
BSR/vjh