Page 1

Section
Program with
Reference Number
Task
Completed By
Frequency
Target Date –First
Implementation
Status
1.2
Availibility of elements
to the target audience
Post information on website. Including
artwork created by school students. Post
information at the community center on a
bulletin board
District Manager
Annually
late 2015
Completed. Will
continue to update thru
out the year
1.3.1
Utility Bill Stormwater
Memo/Inserts
Inserts provided by City of Cedar Park or
City of Austin to be mailed by the district
to residents and businesses. District will
keep record of annual distribution count
District Manager
Oct. 2015
Sept. 2016
Sept. 2017
October 2015
Completed - sent in
October mailing
1.3.2 & 2.3.2
Annual Poster
Campaign
Produce posters and place in parks or
schools. Allow schools to help create
posters. Meet with art teachers
District Manager
Board Committee
Annually
September 2015 thru
April 2016 - Earth Day
In progress - Working
with the elementary
and middles schools
2.3.1
Yearly Public Meetings
Hold Public meeting in district to discuss
stormwater pollution concerns. Advertise
meeting to public 30 days prior to
scheduled date.
Solid Waste
Committee
District Manager
Oct. 2015
Oct. 2016
Oct. 2017
April 2016
Posted agenda 30 days
prior to April 20th
meeting. Presentation
posted on website
2.3.3
Storm drain
Stencil/Tiles
Install informative pollution prevention
tiles to district storm water inlets.
Encourage local participation such as
Boy/Girl Scout Troops & residents.
District Manager
Annually
December 2015
Completed Dec. 2015
Worked with Eagle
Scout to complete
installation 260 tiles
Storm Water Management Program (SWMP) Checklist
 
GJA No. 919-10815-42
1.0
Public Education
2.0
Public Involvement
Prepared by Patricia Rybachek
1
Severn Trent Services
Revised 4/20/2016

Page 2

Section
Program with
Reference Number
Task
Completed By
Frequency
Target Date –First
Implementation
Status
3.2
TPDES Permit
Requiremments
Implement & enforce a program to
detect, investigate, and eliminate illicit
discharges in small MS4. Must include a
plan to detect and address non-
stormwater discharges, including illegal
dumping to the MS4 system.
District Manager
As needed
June 2018 (term end
date)
Survey all 260 storm
drains and inform
residents about how to
keep them cleanb
3.4.1
Storm Sewer Map
District to create storm sewer map
including locations for potential sanitary
system discharges. Copies will be
distributed to schools throughout the
District. Secretary to keep map on hand.
District Engineer
Infratructure
Committee
One time
Existing
Distribution to schools
December 2015
Map updated 3/2016.
Provided storm sewer
map to Paul
(Secretary).
3.4.2
Board Member &
StaffTraining
District to create a list of training
schedule, materials, and procedure for
detecting and reporting illicit discharge.
Board Committee
As Required
September 2015
SOP created. Update
to be more specific.
Train staff and Board.
4.3.1
City of Cedar Park
Development
Specifications
District should review the proposed
development guide to determine all
development within the District is abiding
by the required specifications.
District Engineer
On-going
Current
4.3.2
Site Inspection and
Enforcement
District to record number of
noncompliance citations to development
within District
District Manager
As Required
Current
4.3.3
Construction Plan
Review Procedure
District to distribute construction site
stormwater brochure to contractors and
developers within the district.
District to also record the number of
brochures distributed and maintain a file
copy of the brochure for each year.
District Manager
As Required
Current
4.0
Construction Site Runoff Control
3.0
Illicit Discharge Detection & Eliminaton
Prepared by Patricia Rybachek
2
Severn Trent Services
Revised 4/20/2016

Page 3

Section
Program with
Reference Number
Task
Completed By
Frequency
Target Date –First
Implementation
Status
5.0
Post Construction
Stormwater Mgmt
5.3.1
City of Cedar Park
Development
Specifications
District to maintain copies of manual and
distribute to construction operators.
District Engineer
& Infrastructure
Committee
As Required
Current
No current construction
projects
6.3.1
Catch Basin Cleaning
Drainage System
O&M Schedule
Inspect and clean catch basins as
needed and document cleaning dates,
problem areas and required
maintenance, if needed.
District Manager
On going
Current
Obtaining approval for
inlet survey.
6.3.2
Hazardous Materials
Management
Compile list of materials used within the
district. Research alternatives and
conduct cost/benefit assessment.
Solid Waste
Committee
District Manager
As Required
September 2015
Completed - obtained
list from landscaperand
waste management
6.3.3
Spill Response Kits
District to maintain spill kits and ensure
they are located at appropriate facilities.
District Manager
As Required
Current
Completed.
7.1
Record Keeping
District will store annual reports &
required documents for TCEQ
compliance.
Annual reports are to be presented to the
Board of Directors each year.
District Manager
May 2015
May 2016
May 2017
Current
7.2
Reporting
District will submit annual report to TCEQ
by the anniversary (of the following year)
for each year of the premit term.
District manager
May 2015
May 2016
May 2017
Current
In progress
7.0
Record keeping and
Reporting
6.0
Pollution Prevention / Good
Housekeeping for Municipal Ops
Prepared by Patricia Rybachek
3
Severn Trent Services
Revised 4/20/2016