July 17, 2024 · Regular meeting

Unofficial searchable copy. For the official record, use the district’s own copy.

Engineer's Report, including

Reject change order request from Liberty Civil in the amount of $94,916.00 because the additional pumping expense was the result of the failure of the parts supplier hired by Liberty Civil and that the expense should be borne by the parts supplier and not the taxpayers of the District.
Result
Passed
Moved by
Fabre
Seconded by
Flores
Source
Minutes, regular meeting, July 17, 2024, p. 8, 9